Brackenford Makers Trust · 2023

Brackenford Dairy: 18 maker studios in a 1930s dairy

A locally listed 1930s dairy converted into 18 affordable studios for makers, with a shared kiln room and a café, keeping 86 percent of the original structure.

  • Adaptive reuse
  • Workspace
  • Locally listed
  • Concrete frame

The problem

The Brackenford dairy closed in 2011 and sat empty for nine years. It is a concrete-frame building with brick infill panels, steel Crittall windows and a tall bottling hall, 1,150 m² over two floors. A developer had planning consent to demolish it for flats. The Makers Trust bought it instead, with $3.1 million from a community share offer and a regional regeneration grant.

The brief was 18 studios at below-market rents, from 25 to 70 m², plus a shared kiln and woodwork room that would not disturb anyone. The frame had carbonation and spalling in places, the roof leaked, and the floor slabs carried an unknown load. The building is locally listed, so the bottling hall and the street facade had to read as they always had.

Process

  1. 01

    Survey before sketching

    We spent the first eight weeks measuring, with a structural engineer testing cores from twelve columns. The frame was sound apart from the roof beams, and the slabs could take 5 kN/m², enough for kilns and benches. That result decided the project: keep the frame, repair the concrete and design around what was there.

  2. 02

    Rooms inside the hall

    Rather than subdivide the bottling hall with full-height walls, we placed timber studio boxes inside it, two storeys high with their own roofs. The hall stays legible as one volume, and each studio gets acoustic separation. The original Crittall windows were refurbished and secondary-glazed rather than replaced, keeping the street facade intact.

  3. 03

    Phased so tenants could move in early

    The trust needed rent coming in before the building was finished. We split the work into two phases: the ground floor and kiln room first, then the upper hall. Eight tenants moved in after fourteen months, and their rents covered the loan interest during phase two.

01Street facade with refurbished Crittall windows, secondary-glazed
02Section through the bottling hall and two-storey timber studio boxes
03First-floor plan, studios of 25 to 70 m², 1:200
04Axonometric of phase one and phase two
05Shared kiln and woodwork room on the ground floor
06Repaired concrete column next to new birch-ply studio wall

Outcome

All 18 studios were let before phase two finished, with a waiting list of 40. Keeping 86 percent of the structure saved an estimated 610 tonnes of embodied carbon compared with the demolition scheme. Total construction cost came to $2,700 per m², well below a new build of the same size.

1,150m²
Gross internal area
86%
Original structure kept
$2,700
Construction cost per m²
Every other architect started with a demolition option. Barrow Field Studio started with a core drill and an engineer, and that saved the building and about a year of arguments.
Owen MarchettiChair, Brackenford Makers Trust

Have a site, a building or just a question?

Most of our projects start with a site visit and a cup of tea. Tell us what you have in mind, and we will tell you honestly what it might take.

Free first conversation · Fixed-fee feasibility studies

Live demo · Barrow Field Studio— View template →